100000 t / year

Project Challenges
The project required the construction of a new system while keeping the existing production running without shutdown. Meanwhile, the site was space-constrained, the hoisting and transportation routes were complicated, and the original system featured diverse interfaces.
Implementation Highlights
A dedicated transportation and hoisting plan was developed for the project. Special technical design was carried out for complex process interfaces to ensure stable connection between the new and old systems.
Project Outcomes
The construction of new production capacity was completed without shutting down the original production, preparing the customer for commissioning during the peak season.